Side of road extending into middle of road
Reported in the Pothole category anonymously at 07:57, Tue 15 May 2018
Sent to Buckinghamshire Council 3 minutes later. FixMyStreet ref: 1312281.
Very deep potholes litter Dollicot presenting danger to pedestrians, cyclists and potential damage to vehicles which ultimately becomes the responsibility of the council after the problem has been reported. This road is in a terrible state of repair and needs immediate attention.
Updates
-
Thank you for your report which is currently under review.
We will investigate this and respond to you within 10 working days.
We will continue to update you by email when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshireFed up with potholes – we are too!
Government funding cuts and pressures from other services such as social care means there isn’t enough money to pay for all the work which needs doing on our roads.
However, a new single council for Buckinghamshire would save at least £18m per year – money which the new council could decide to put into more road resurfacing.
The Government wants to hear your views on the plans. Visit www.buckscc.gov.uk/OneCouncil to have your say – it only takes a minute!Posted by Buckinghamshire Council at 08:00, Tue 15 May 2018
-
State changed to: In progress
Updated by Buckinghamshire Council at 13:27, Tue 15 May 2018
-
We have completed our inspection of the defect, which will now be repaired within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 13:27, Tue 15 May 2018
-
Thank you for your report, the repair of this defect is now in progress.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshireState changed to: In progress
Posted by Buckinghamshire Council at 10:50, Fri 8 June 2018
-
Thank you for your report the repair of this defect is now complete.
Regards
Transport for BuckinghamshireState changed to: Fixed
Posted by Buckinghamshire Council at 10:50, Fri 8 June 2018
This report is now closed to updates from the public. You can make a new report in the same location.