2 metre long pothole, and rapidly increasing, southbound side

Reported in the Road surface category by Geoff Sheddick at 17:35, Fri 9 November 2018

Received by Buckinghamshire County Council moments later

Approx 5 metres from the beginning of the southbound carriageway, towards the middle of the road, a > 2 metres long x > 30cm wide pothole is rapidly deepening and lengthening, where the surface is being eroded by the offside wheels of southbound vehicles. It only becomes visible to drivers turning into Sheepridge Lane from Heath End Road [whether coming from either the east or from the west] when they are already committed to the turn, and when it is difficult and/or dangerous to make the rapid change of direction needed to avoid the hole.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and respond to you within 10 working days.
    We will continue to update you by email when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 17:40, Fri 9 November 2018

  • Thank you for your report.
    We have inspected the defect in line with our Highway Safety Inspection Policy, and the defect does not currently meet the criteria for immediate intervention. This enquiry is now closed, but details of the defect will remain on our system and will continue to be inspected in line with our policy. Further updates will not be given on this enquiry.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 11:52, Mon 19 November 2018

  • State changed to: In progress

    Updated by Buckinghamshire County Council at 11:52, Mon 19 November 2018

  • Thank you for your report.
    We have inspected the defect in line with our Highway Safety Inspection Policy, and the defect does not currently meet the criteria for immediate intervention. This enquiry is now closed, but details of the defect will remain on our system and will continue to be inspected in line with our policy. Further updates will not be given on this enquiry.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 11:52, Mon 19 November 2018

  • State changed to: In progress

    Updated by Buckinghamshire County Council at 14:33, Mon 19 November 2018

  • Still open, via questionnaire, 18:10, Fri 7 December 2018