Fixed
Corner of Sycamore Dean
Reported in the Street light not working category anonymously at 09:50, Sat 23 February 2019
Sent to Buckinghamshire Council 4 minutes later. FixMyStreet ref: 1552589.
Dear Sir Madam
We have just had a new lamppost fitted yesterday after a 1960's post was removed and both my neighbour and myself did ask the guys fitting it, a shade would most likely be needed, and last night as expected it blasted light into both our homes. Could we request a shade so it is shinning on the road please.
Best regards
Mr G Keyte
1 Woodcroft Rd HP53JU
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 09:55, Sat 23 February 2019
-
Thank you for your report.
We have assessed your report and the repair of this defect has been added to our programme of works.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshireState changed to: Action scheduled
Posted by Buckinghamshire Council at 15:14, Wed 27 February 2019
-
State changed to: In progress
Updated by Buckinghamshire Council at 15:15, Wed 27 February 2019
-
State changed to: Fixed
Updated by Buckinghamshire Council at 15:57, Wed 27 February 2019
-
This is not fixed! No shade fitted yet?
Posted anonymously at 17:54, Wed 27 February 2019
-
State changed to: In progress
Updated by Buckinghamshire Council at 08:04, Thu 21 March 2019
-
Thank you for your report, the repair of this defect is now in progress.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 11:04, Mon 1 April 2019
-
We are pleased to tell you that the repair of this defect is now complete.
The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 11:11, Mon 1 April 2019
-
State changed to: In progress
Updated by Buckinghamshire Council at 15:33, Tue 2 April 2019
-
We are pleased to tell you that the repair of this defect is now complete.
The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 12:18, Wed 3 April 2019
This report is now closed to updates from the public. You can make a new report in the same location.