Dropped kerb outside 33 Hillington Close HP19 7SG

Reported in the Kerb damage / issue category anonymously at 10:50, Monday 8 April 2019

Received by Buckinghamshire County Council moments later

The dropped kerb here needs repair please. The stones are loose and there is concern that these will start to damage the underside of the car. Please inspect and repair. Thank you.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 10:56, Monday 8 April 2019

  • Thank you for your report.
    We have assessed your report and the repair of this defect has been added to our programme of works.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 12:49, Friday 12 April 2019

  • State changed to: In progress

    Updated by Buckinghamshire County Council at 14:33, Friday 12 April 2019

  • I have recently been alerted to this matter and inspected at the weekend. The kerb stones here move up and down by several inches when stepped on, no doubt the weight of vehicles continually passing over will soon make this a bigger risk for damage to vehicles and injury to pedestrians. Please can this be regarded as a high priority repair? Many thanks, Cllr Mike Smith AVDC

    Posted by Mike Smith at 10:03, Monday 3 June 2019

  • Thank you for your report, the repair of this defect is now in progress.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 09:30, Monday 12 August 2019

  • Thank you for your report, the repair of this defect is now in progress.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 15:33, Tuesday 13 August 2019