Reported in the Road surface category anonymously at 07:31, Tuesday 14 May 2019

Received by Buckinghamshire County Council moments later

There is subsidence in the pavement and it has been getting worse over the last few months, there is also a raised ridge in the road that may well damage car suspensions since the road should be level at that point in the road. this has been raised before and told it has been fixed,, it has not been fixed, simply fenced off. when will it be fixed?

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 07:35, Tuesday 14 May 2019

  • Thank you for your report.
    An initial assessment has been made and further work to investigate your enquiry is required. This should be completed within the next 10 days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 09:16, Wednesday 15 May 2019

  • We have contacted you separately regarding this, and this enquiry is now closed.
    Regards
    Transport for Buckinghamshire

    State changed to: Closed

    Posted by Buckinghamshire County Council at 09:30, Monday 3 June 2019

  • Hi, i was informed via email of the following "The road is due to under go investigation works by our contractors, there are process which need to be followed before they can excavate which are being taken. We anticipate the works will be starting by the end of the week. We will continue to monitor until the works are in progress." nothing has happened since i received that email on the 3rd June, the road is still closed off but no works have started. can someone please provide a date by when this will start? thanks.

    State changed to: Open

    Posted anonymously at 06:57, Thursday 20 June 2019

  • We have contacted you separately regarding this, and this enquiry is now closed.
    Regards
    Transport for Buckinghamshire

    State changed to: Closed

    Posted by Buckinghamshire County Council at 08:42, Monday 1 July 2019