Back to all reports

6 Long Meadow

Reported in the Blocked drain category anonymously at 10:37, Wednesday 14 August 2019

Received by Buckinghamshire County Council moments later

Enquiry number 46068966 It is not the gully itself that is the problem, this was sucked out a couple of years ago. In Greenway (the road Long Meadow comes off of) there are soakaways attached to all the gullies as there is in Long Meadow.About seven years ago those in Greenway were all sucked out, but not those in Long Meadow. We've lived here for 28 years and they have never been done. As you can see from the first Photo when there is excessive rainfall we get all the water from Greenway coming down the hill into Long Meadow and down our gully. This then overflows the soakaway and runs down the drive. There are two of these soakaways in my front garden so it must have been recognized as a problem when the houses were built. So can you please suck them out.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 10:41, Wednesday 14 August 2019

  • Thank you for your report.
    We have assessed your report and the repair of this defect has been added to our programme of works.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 14:12, Thursday 15 August 2019

  • State changed to: In progress

    Updated by Buckinghamshire County Council at 14:13, Thursday 15 August 2019

  • State changed to: Open

    Updated by Buckinghamshire County Council at 09:22, Tuesday 24 September 2019

  • State changed to: Internal referral

    Updated by Buckinghamshire County Council at 13:39, Thursday 26 September 2019

  • We are pleased to tell you that the repair of this defect is now complete.

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire County Council at 07:23, Monday 28 October 2019

This report is now closed to updates. You can make a new report in the same location.