Back to all reports

Crossing of the North Orbital Road

Reported in the Blocked drain category anonymously at 10:44, Thu 15 August 2019

Received by Buckinghamshire Council moments later

Despite drainage works recently the crossing is continuing to flood.

"It was quite coincidental when the so called drainage works were on-going the drain opening in the kerb adjacent to the crossing was cleared by one of the workmen using his hand to remove some of the material which had accumulated at the top where the drainage hole is. The blockage has not been properly cleared and as soon as it rains the road will flood again and the problem has not been corrected. The residents at Denham Green have put up with having to wade across the road and hope to avoid not becoming drenched with spray from passing traffic for many years and urgent action is once again required to put this matter right.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 10:45, Thu 15 August 2019

  • Thank you for your report.
    We have assessed your report and the repair of this defect has been added to our programme of works.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 10:02, Mon 2 September 2019

Only the original reporter may leave updates. If you made the original report please log in to leave an update.