The blocked gully is located at the bottom of Trees Road and floods the pavement with silt and stones, and creates big puddles in Valley Road.

Reported in the Flooded subway category anonymously at 17:10, Thursday 17 October 2019

Received by Buckinghamshire County Council moments later

The concrete gully that lies across the full width of the bottom of Trees Road has small circular holes in it like a kitchen calendar which get blocked with stones that roll down the unmade surface of Trees Road. When there is heavy rain lots more stones and silt get carried forward and finally become deposited on the pavement and in Valley Road. This in turn blocks the drains in Valley Road and flooding occurs. Pedestrians complain because they get wet/splashed when vehicles drive past. The area is dangerous for wheelchair users because the road and pavement surface is unstable and their wheelchairs could tip over whilst trying to avoid the mess. This has been a continued problem over many years and residents who walk up and down Valley Road are fed up with the problem.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 17:15, Thursday 17 October 2019

  • Thank you for your report.

    This has been added to our programme of works. Unfortunately, we are unable to provide you with a timescale for this work to be carried out, we work on a priority based risk matrix in line with our Highway Inspection Policy and therefore programme times can change due to priority based working.

    Please be assured this is on our list of works to be carried out, we will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below;
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 09:56, Thursday 24 October 2019

  • State changed to: In progress

    Updated by Buckinghamshire County Council at 09:56, Thursday 24 October 2019

  • Thank you for your report.

    This has been added to our programme of works. Unfortunately, we are unable to provide you with a timescale for this work to be carried out, we work on a priority based risk matrix in line with our Highway Inspection Policy and therefore programme times can change due to priority based working.

    Please be assured this is on our list of works to be carried out, we will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below;
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 09:56, Thursday 24 October 2019

  • State changed to: In progress

    Updated by Buckinghamshire County Council at 10:55, Thursday 24 October 2019

Provide additional information