Back to all reports

At the top of the close, outside numbers 9 & 10 CHEQUERS CLOSE

Reported in the Pothole category anonymously at 10:05, Saturday 2 November 2019

Received by Buckinghamshire County Council moments later

The pothole has been increasing in size and depth.... When driving on/reversing off the driveway for any of the houses at the top of the close, its getting harder to avoid it, risking damage to cars and tyres, and a tripping hazard for pedestrians

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 10:10, Saturday 2 November 2019

  • Thank you for your report.

    This has been added to our programme of works. Unfortunately, we are unable to provide you with a timescale for this work to be carried out, we work on a priority based risk matrix in line with our Highway Inspection Policy and therefore programme times can change due to priority based working.

    Please be assured this is on our list of works to be carried out, we will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below;
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 13:34, Friday 8 November 2019

  • State changed to: Open

    Updated by Buckinghamshire County Council at 16:50, Monday 11 November 2019

  • As per telephone conversation earlier with Sabrina, they came out today and fixed the pot hole, they did a fantastic job, a proper fix not just a temporary one, we were due to be going out, so I asked how long we'd need to wait for it to go off, to which they said 5 or 10 minutes... So we waited... However within less than a minute they promptly drove right over the top of their repair, leaving a sunken area where they had just fixed it.... Picture above shows the damage to the repair

    Posted anonymously at 17:05, Monday 11 November 2019

  • Thank you for your report.

    This has been added to our programme of works. Unfortunately, we are unable to provide you with a timescale for this work to be carried out, we work on a priority based risk matrix in line with our Highway Inspection Policy and therefore programme times can change due to priority based working.

    Please be assured this is on our list of works to be carried out, we will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below;
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 11:44, Tuesday 12 November 2019

  • We have contacted you separately regarding this, and this enquiry is now closed.
    Regards
    Transport for Buckinghamshire

    State changed to: Closed

    Posted by Buckinghamshire County Council at 11:44, Tuesday 12 November 2019

This report is now closed to updates. You can make a new report in the same location.