Back to all reports

Outside 6, 8 & 10 Lakes Lane.

Reported in the Footpath / pavement problem category anonymously at 10:15, Friday 17 January 2020

Received by Buckinghamshire Council moments later

Grill missing from drainage channel. Causing a danger to pedestrians and young children on bikes. Please repair as soon as possible.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 10:21, Friday 17 January 2020

  • Thank you for your report.
    An initial assessment has been made and further work to investigate your enquiry is required. This should be completed within the next 10 days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 15:34, Friday 31 January 2020

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 08:39, Monday 17 February 2020

  • State changed to: In progress

    Updated by Buckinghamshire Council at 08:39, Monday 17 February 2020

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 08:40, Monday 17 February 2020

  • State changed to: In progress

    Updated by Buckinghamshire Council at 14:58, Monday 17 February 2020

  • Thank you for your report, the repair of this defect is now in progress.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 12:00, Friday 21 February 2020

  • State changed to: Open

    Updated by Buckinghamshire Council at 14:56, Monday 24 February 2020

Only the original reporter may leave updates. If you made the original report please log in to leave an update.