Across the access to 23 & 25 Harwood Road
Reported in the Pothole category anonymously at 11:31, Fri 31 January 2020
Sent to Buckinghamshire Council 5 minutes later
18 & 32 tonne lorries delivering to the site opposite have damaged the road surface to a current depth of approx 4" in places creating a furrow which is unavoidable when entering or leaving. It would appear to be causing damage along a former trench which may contain some sort of utility supply.
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 11:35, Fri 31 January 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 09:58, Wed 12 February 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 09:58, Wed 12 February 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 09:58, Wed 12 February 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 14:59, Wed 12 February 2020
-
Thank you for your report, the repair of this defect is now in progress.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 09:40, Mon 17 February 2020
-
We are pleased to tell you that the repair of this defect is now complete.
The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 09:41, Mon 17 February 2020
This report is now closed to updates. You can make a new report in the same location.