Fixed
Pothole on lefthand side of carriageway when driving North
Reported in the Pothole category anonymously at 09:25, Sat 15 February 2020
Sent to Buckinghamshire Council 5 minutes later. FixMyStreet ref: 1999608.
A pothole, that was repaired at the beginning of Jan 2020 has reopened up. It is in the line of driving, it is deep and is causing cars to swerve around it. As a rate payer, realising that these repairs are not done for free, please can you ensure that the next repair is of better quality and will last longer than 5 weeks before it fails. At this rate you will be repairing this one pot hole over 10 times this year alone. And that will be very expensive to me !!
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 09:30, Sat 15 February 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within two working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 10:09, Mon 17 February 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 10:09, Mon 17 February 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within two working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 10:10, Mon 17 February 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 14:59, Mon 17 February 2020
-
Thank you for your report, the repair of this defect is now in progress.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 10:03, Wed 19 February 2020
-
We are pleased to tell you that the repair of this defect is now complete.
The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 10:04, Wed 19 February 2020
This report is now closed to updates from the public. You can make a new report in the same location.