Reported in the Light on during the day category anonymously at 10:48, Fri 17 April 2020
Sent to Buckinghamshire Council 2 minutes later. FixMyStreet ref: 2090019.
This Lamp LC001 has now been on during the day for almost three years. If replacement parts not available could it be switched off to save council money?
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 10:50, Fri 17 April 2020
-
Thank you for your report.
We have recorded it and will consider it when we are planning future works in the area. Please note we work on a priority based risk matrix in line with our Highway Inspection Policy and therefore programme times can change due to priority based working.
Our Highways Inspection Policy can be accessed via the link below;
www.buckscc.gov.uk/highwaysinspectionpolicy
Regards
Transport for BuckinghamshireState changed to: Action scheduled
Posted by Buckinghamshire Council at 12:46, Fri 17 April 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 12:47, Fri 17 April 2020
-
Thank you for your report, the repair of this defect is now in progress.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 11:04, Fri 24 April 2020
-
Our street lighting crew have attended the fault and found that either the equipment is damaged beyond repair or has reached the end of its serviceable life.
A works order has been raised to replace the asset and this has been placed in a programme of works which will be completed as soon as possible.
Regards
Transport for BuckinghamshireState changed to: Open
Posted by Buckinghamshire Council at 11:05, Fri 24 April 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 09:08, Thu 23 July 2020
-
Thank you for your report, the repair of this defect is now in progress.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 01:29, Fri 31 July 2020
-
We are pleased to tell you that the repair of this defect is now complete.
The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 01:53, Fri 31 July 2020
This report is now closed to updates from the public. You can make a new report in the same location.