Fixed
Outside houses Eryl,Green Baulk & railway bridge 13
Reported in the Blocked drain category anonymously at 15:03, Mon 27 July 2020
Sent to Buckinghamshire Council less than a minute later. FixMyStreet ref: 2218762.
Due to cycle path installation work, mud,grit & stones have blocked drains of which one is collapsing.
Due to length of cycle path works, traffic lights were in place for a matter of months, this caused lorries to mount path outside houses & formed a rut on footpath which is used by playgroup children
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 15:03, Mon 27 July 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 07:55, Tue 28 July 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 07:55, Tue 28 July 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 07:55, Tue 28 July 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 14:22, Tue 28 July 2020
-
Thank you for your report, the repair of this defect is now in progress.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 08:27, Mon 3 August 2020
-
We are pleased to tell you that the repair of this defect is now complete.
The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 09:13, Mon 3 August 2020
This report is now closed to updates from the public. You can make a new report in the same location.