Raised manhole cover dangerous to pedestrians in area with inadequate street lights. Reported to BCC Highways Dept after this manhole cover caused me to have a bad fall. My call was on 17June 1919. This was recorded with a Ref No 460681197 I know other people have also had accidents. No action taken despite follow up calls to Highways. White lines marked at scene after I used a Marlow Facebook site to warn other residents of this danger....no action taken by Highways since.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 12:16, Monday 21 September 2020

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:32, Wednesday 23 September 2020

  • State changed to: In progress

    Updated by Buckinghamshire Council at 11:32, Wednesday 23 September 2020

  • Thank you for your report, the repair of this defect is now in progress.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 12:54, Tuesday 29 September 2020

  • We are pleased to tell you that the repair of this defect is now complete.

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 12:54, Tuesday 29 September 2020

  • The raised manhole cover has had a small amount of asphalt tipped on it, but so roughly done it is probably not going to last long! One kerb stone put back in place,one still missing.

    State changed to: Open

    Posted by Janet Harper at 15:43, Monday 19 October 2020
    Still open, via questionnaire

  • State changed to: Internal referral

    Updated by Buckinghamshire Council at 09:33, Tuesday 20 October 2020

This report is now closed to updates. You can make a new report in the same location.