Back to all reports

Wall collapsed

Reported via Android in the Kerb damage / issue category anonymously at 09:53, Thu 19 November 2020

Received by Buckinghamshire Council moments later

Wall running along Beaconsfield Road along the front on the property's named Hillside Cottages has collapsed. Bricks blocking pavement.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 09:53, Thu 19 November 2020

  • Thank you for your report.
    An initial assessment has been made and further work to investigate your enquiry is required. This should be completed within the next 10 days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 10:10, Wed 25 November 2020

  • Thank you for your report.

    This has been added to our programme of works. Unfortunately, we are unable to provide you with a timescale for this work to be carried out, we work on a priority based risk matrix in line with our Highway Inspection Policy and therefore programme times can change due to priority based working.

    Please be assured this is on our list of works to be carried out, we will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below;
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 09:44, Mon 21 December 2020

  • State changed to: In progress

    Updated by Buckinghamshire Council at 09:44, Mon 21 December 2020

  • Thank you for your report.

    This has been added to our programme of works. Unfortunately, we are unable to provide you with a timescale for this work to be carried out, we work on a priority based risk matrix in line with our Highway Inspection Policy and therefore programme times can change due to priority based working.

    Please be assured this is on our list of works to be carried out, we will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below;
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 09:45, Mon 21 December 2020

  • State changed to: In progress

    Updated by Buckinghamshire Council at 09:50, Mon 21 December 2020

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 10:16, Tue 29 December 2020

  • We are pleased to tell you that the repair of this defect is now complete.

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 10:17, Tue 29 December 2020

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: In progress

    Posted by Buckinghamshire Council at 11:23, Tue 29 December 2020

  • We are pleased to tell you that the repair of this defect is now complete.

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 09:22, Wed 30 December 2020

  • State changed to: In progress

    Updated by Buckinghamshire Council at 12:28, Thu 31 December 2020

  • State changed to: Open

    Updated by Buckinghamshire Council at 09:46, Tuesday 5 January 2021

Only the original reporter may leave updates. If you made the original report please log in to leave an update.