Lamp posts on the footpath between Hennerton Way and Roebuck Ave (NOT the lamp posts on the road on Hennerton Way) lamp posts outside the front of No. 40 and No.35

Reported via desktop in the Street light not working category anonymously at 23:27, Saturday 16 January 2021

Received by Buckinghamshire Council moments later

I have reported these lamps being our several times over the past 3 years. The latest reply to report ref. no. 40149727 states that these have been fixed. This is definitely not true. The lights on the footpath at the front of our houses are definitely not working. It is pitch black along here at night so walking back to our homes at night is extremely risky and I am worried sooner or later someone is either going to have a nasty accident or, worse still, get mugged or assaulted. Please treat this with great urgency as they have been out for over 3 years now. I have already had a nasty fall as stated in my report when going to put the bins out and fractured my thumb falling on the path in the dark. I am very happy to meet anyone who would like me to show them which lamp posts are not working. My mobile number is 07931 575371. These are NOT the lamp posts on the road but on the footpath between our houses and the hedgerow seperating us from Roebuck Ave,

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 23:27, Saturday 16 January 2021

  • Thank you for your report; the repair has been added to our programme of works.
    Unfortunately, we are unable to provide you with a timescale for this work to be carried out as we programme the work on a priority basis (in line with our Highway Inspection Policy). This does mean that sometimes planned programme times may need to be changed due to priority based working.
    Please be assured this problem is on our list of works to be carried out. We will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below:
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 13:37, Sunday 17 January 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 13:38, Sunday 17 January 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 13:02, Wednesday 27 January 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 13:03, Wednesday 27 January 2021

This report is now closed to updates. You can make a new report in the same location.