Large pothole very dangerous

Reported via mobile in the Pothole category anonymously at 11:59, Friday 19 February 2021

Received by Buckinghamshire Council moments later

Huge hole in middle of road

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 12:00, Friday 19 February 2021

  • Thank you for your report.
    An initial assessment has been made and further work to investigate your enquiry is required. This should be completed within the next 10 days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 15:42, Wednesday 17 March 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:01, Thursday 18 March 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 11:01, Thursday 18 March 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:01, Thursday 18 March 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 16:20, Thursday 18 March 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.