Back to all reports

Pothole

Reported via iOS in the Pothole category anonymously at 13:58, Sat 27 February 2021

Received by Buckinghamshire Council moments later

About 5 inches deep. Dangerous, particularly as cyclists have to move into the narrow road to avoid it, and there are big truck belonging to the builders yard coming up and down. This is an important issue that needs to be addressed before someone is hurt or killed.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 13:58, Sat 27 February 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 08:04, Mon 1 March 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 08:04, Mon 1 March 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: In progress

    Posted by Buckinghamshire Council at 08:59, Thu 4 March 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 09:28, Thu 4 March 2021

This report is now closed to updates. You can make a new report in the same location.