Whole of Ardenham Street has never been finished with the resurfacing work and is now sinking and there are no road markings which means car are parking dangerously causing problems for waste collection and deliveries.

Reported via desktop in the Road surface category anonymously at 19:35, Friday 5 March 2021

Received by Buckinghamshire Council moments later

There is a pothole/sinkage opposite number 17 that is about 8 inches deep now and getting wider each day and now causing a risk for pedestrians and car drivers. This road has been like this for the last year due to one vehicle belonging to number 25 refusing to move the car for teh work to be completed and now everyone is suffering. When is this going to be finished as the refuse trucks have become stuck more than once . They took photo's of the issues so you can refer to them for further information.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 19:35, Friday 5 March 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 08:19, Monday 22 March 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 08:19, Monday 22 March 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 08:20, Monday 22 March 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 12:45, Monday 22 March 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 09:43, Thursday 1 April 2021

This report is now closed to updates. You can make a new report in the same location.