Back to all reports

S2443 - Two overhead sign lights failed

Reported via desktop in the Sign light not working category anonymously at 11:31, Monday 17 May 2021

Received by Buckinghamshire Council moments later

Photo of this report zoom

Redact

S2443 - Two overhead sign lights failed.

Please repair or remove, thanks.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 11:31, Monday 17 May 2021

  • Thank you for your report.
    We have inspected the defect and will aim to repair within 6-8 weeks.
    We will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below:
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 14:14, Monday 17 May 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 14:15, Monday 17 May 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 10:54, Thursday 20 May 2021

  • Our street lighting crew have attended the fault and found that either the equipment is damaged beyond repair or has reached the end of its serviceable life.
    A works order has been raised to replace the asset and this has been placed in a programme of works which will be completed as soon as possible.
    Regards
    Transport for Buckinghamshire

    State changed to: Open

    Posted by Buckinghamshire Council at 11:13, Thursday 20 May 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 14:56, Thursday 20 May 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 10:08, Tuesday 25 May 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 10:12, Tuesday 25 May 2021

This report is now closed to updates. You can make a new report in the same location.