Fixed
Approx 200yards from Terrick roundabout end of Chalkshire Road
Reported via desktop in the Pothole category anonymously at 14:20, Tue 8 June 2021
Sent to Buckinghamshire Council less than a minute later. FixMyStreet ref: 2777274.
There are two adjacent drain covers on the west side of the road, where the surrounding tarmac has broken away forming a pothole. One of these has at some point been marked with white paint so must already be on your repair schedule. The other has not been marked. Both of these drain covers are lying loose within their respective holes. Both of these must be dangerous to cyclists to hit or swerve to avoid. ALSO both of these make a loud CLIDOINK noise every time a vehicle goes over each drain. This occurs up to several times per minute. The noise is very loud and must exceed acceptable environmental noise levels. This is extremely disturbing for local residents, including us. This problem has existed for several weeks, probably months. Many thanks for fixing this issue promptly.
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 14:20, Tue 8 June 2021
-
Thank you for your report.
An initial assessment has been made and further work to investigate your enquiry is required. This should be completed within the next 10 days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 13:46, Tue 15 June 2021
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 10:00, Tue 29 June 2021
-
State changed to: In progress
Updated by Buckinghamshire Council at 10:00, Tue 29 June 2021
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 10:03, Tue 29 June 2021
-
State changed to: In progress
Updated by Buckinghamshire Council at 12:57, Tue 29 June 2021
-
Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 10:14, Fri 2 July 2021
-
We are pleased to tell you that the repair of this defect is now complete.
Please consider completing our short survey below on how you found the repair;
https://forms.gle/ FywWv2ZGrGb9XgCu8The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 10:14, Fri 2 July 2021
This report is now closed to updates from the public. You can make a new report in the same location.