Edge of road fallen away/badly damaged opposite where Thames water are working

Reported via mobile in the Pothole category by Tracy Russell at 17:58, Thu 10 June 2021

Sent to Buckinghamshire Council less than a minute later

Due to Water works on the opposite side of the road this very deep rut is highly dangerous

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 17:58, Thu 10 June 2021

  • Thank you for your report.
    We have inspected the defect and will aim to repair within 6-8 weeks.
    We will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below:
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 09:49, Tue 22 June 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 09:50, Tue 22 June 2021

  • Thank you for your report.
    We have inspected the defect and will aim to repair within 6-8 weeks.
    We will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below:
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 09:50, Tue 22 June 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 11:14, Tue 22 June 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 09:41, Mon 5 July 2021