Back to all reports

Treadway hill loudwater

Reported via mobile in the Weed problem on the highway category anonymously at 23:05, Tuesday 15 June 2021

Received by Buckinghamshire Council moments later

Photo of this report zoom

Redact

Photo of this report zoom

Redact

Photo of this report zoom

Redact

Overgrown hedges and weeds . You can not walk on the pavement as there is a lot off overgrown weeds and hedges. Also this is a school walking route please cut back soon.? Also the main roundabout at loudwater near Tesco is very overgrown you can not see cars approaching.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 23:05, Tuesday 15 June 2021

  • Thank you for your report.
    We have inspected the defect and will aim to repair within 6-8 weeks.
    We will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below:
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 08:21, Wednesday 16 June 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 08:21, Wednesday 16 June 2021

  • Thank you for your report.
    We have inspected the defect and will aim to repair within 6-8 weeks.
    We will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below:
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 08:22, Wednesday 16 June 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 14:33, Wednesday 16 June 2021

  • Photo of this report zoom

    Redact

    Photo of this report zoom

    Redact

    Photo of this report zoom

    Redact

    Please cut these bushes back soon you can not even walk passed on the pavement. I don’t understand why it takes 8 weeks to come and cut the bushes? This is a main school route as well where children can not even walk passed . Thank you .

    Posted anonymously at 19:34, Monday 28 June 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 10:08, Tuesday 20 July 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 11:26, Tuesday 20 July 2021

This report is now closed to updates. You can make a new report in the same location.