The storm drain on the layby opposite the council depot on London Road East

Reported via desktop in the Blocked drain category anonymously at 17:52, Fri 18 June 2021

Received by Buckinghamshire Council moments later

This issue was reported on 14/6/2021. Although, the drain has been blocked for several years it is only a problem after a major rain fall. However, there has been a sewage overflow. Thames Water have stopped any further sewage overflow but the area now has raw sewage. The recent heavy rainfall has resulted in layby having several feet of sewage as per the attached photos. Since we expect several more days of very heavy rainfall, I am concerned that we might have an environmental problem unless the drain is cleared soon.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 17:52, Fri 18 June 2021

  • Thank you for your report. Although this does not meet our criteria for requiring immediate attention, this defect will be added to our records for the future.

    Our records will be used to generate larger planned works and will also enable us to pick up this defect when we are carrying out repairs of a similar nature in the area.
    Thank you for taking the time to bring this matter to our attention.

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:47, Tue 29 June 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 11:48, Tue 29 June 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 09:19, Fri 2 July 2021