Back to all reports

Blocked drainage

Reported via desktop in the Blocked drain category anonymously at 23:39, Friday 16 July 2021

Received by Buckinghamshire Council moments later

This drain gets blocked every time we bit of rain. Has been issue for few years cannot understand why not fixed.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 23:39, Friday 16 July 2021

  • Hello

    This is front instron offices and you can get free shower if you are walking the pavement. Please kindly check today as it is raining and you will see it.

    Posted anonymously at 13:13, Friday 30 July 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:51, Thursday 12 August 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 11:51, Thursday 12 August 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:51, Thursday 12 August 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 08:13, Friday 13 August 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 08:24, Thursday 19 August 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 10:10, Thursday 19 August 2021

This report is now closed to updates. You can make a new report in the same location.