Back to all reports

Pavement in disrepair

Reported via desktop in the Footpath / pavement problem category anonymously at 19:14, Monday 19 July 2021

Received by Buckinghamshire Council moments later

The stretch of pavement from Limes Avenue to Howard Avenue is almost entirely damaged, resulting in multiple crevices, cracks and potholes. This is particularly hazardous to parents with pushchairs and those with mobility issues. It has been like this at least two years and is progressively getting worse.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 19:14, Monday 19 July 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 08:28, Thursday 22 July 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 08:28, Thursday 22 July 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 10:21, Thursday 22 July 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: In progress

    Posted by Buckinghamshire Council at 09:20, Tuesday 27 July 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 10:07, Tuesday 27 July 2021