Back to all reports

It before the bus stop the road is john hall way high wycombe bucks a stupid 40 ton vehicle has broken damage your drain cover and is very dangerous your

Reported via desktop in the Blocked drain category anonymously at 12:36, Friday 3 September 2021

Received by Buckinghamshire Council moments later

A stupid 40 ton vehicle has broken damage your drain cover and is very dangerous. it before the bus stop Nancy hall court bus stop the road is called John hall way high wycombe bucks / its very urgent can you get your Work team to repair ASAP this broken drain cover

Why you let a 40 ton vehicle park there there and is doing big damage to your road and drain cover and your grass verg is damage with there big wheels this road is not a trucks to park there ??????

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 12:36, Friday 3 September 2021

  • Thank you for your report.
    We have inspected the defect and will aim to repair within 6-8 weeks.
    We will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below:
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:06, Wednesday 8 September 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 11:06, Wednesday 8 September 2021

  • Thank you for your report.
    We have inspected the defect and will aim to repair within 6-8 weeks.
    We will continue to monitor all defects to ensure the safety of our residents as part of our Highways Inspection Policy which can be accessed via the link below:
    www.buckscc.gov.uk/highwaysinspectionpolicy
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:07, Wednesday 8 September 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 13:18, Thursday 9 September 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 08:30, Wednesday 6 October 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 09:55, Wednesday 6 October 2021

This report is now closed to updates. You can make a new report in the same location.