You can move around with your keyboard
plus
minus
left
right
Drop pin on the map to start a new report
space
Press space again to adjust the location
space
Back to all reports

Opposite 105 in front of double garages

Reported via desktop in the Pothole category anonymously at 12:36, Sun 26 September 2021

Sent to Buckinghamshire Council less than a minute later

There are 2 holes one about 3 to 4 inches deep and approx 2 ft wide. These have been filled in the past and have failed again. It needs be repaired properly and not patched as it is causing stones to be thrown up over cars as they are continually bumping down it or driving on the pavement to try and avoid them. They are deep enough to cause damage to cars going into them. This has been an ongoing problem as they are only ever patched. The current hole has been there for probably in excess of 3 months therefore it is deteriorating rapidly.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 12:36, Sun 26 September 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 15:01, Tue 28 September 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 15:01, Tue 28 September 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 15:02, Tue 28 September 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 10:37, Wed 29 September 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 08:31, Tue 5 October 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 09:38, Tue 5 October 2021

This report is now closed to updates. You can make a new report in the same location.